MAJOR PROJECTS FOR 2003

NORTHLAND PLAZA SHOPPING CENTER

    Location:

    DeKalb, IL

    Parties:

    Joseph Freed and Associates and Pepper Construction

    Facilities:

    Reconstructed Shopping Mall with New Stores Including Elder-beerman, Penny’s, Borders, and Bed Bath and Beyond

    Tonnage:

    Over 10,000 Tons of  Mix

    Services:

    Overlay ,Reconstruction, and Reconfiguration, of Existing Parking Lot, and Widening and Overlay of County Road with New Curb and Gutter.

    Budget:

    $2,400,000.

    Time Frame:

    Fall of 2002 and Spring of 2003 Including Final Surface Placed at Night So as to Not Disrupt Existing Newly Opened Stores.

Del Webb

    Location:

    Huntley, IL

    Parties:

    Pulte Homes

    Facilities:

    Roadways for New Residential Subdivisions

    Tonnage:

    Over 15000 Ton Asphalt and over 30,000 Ton Stone

    Services:

    Stone Base and Asphalt Paving for New Roadways

    Budget:

    In excess of $1,000,000

    Time Frame:

    Various Completion Dates in 2003

Lake Couunty Highway Department Peterson Road

    Location:

    Lake County, IL

    Parties:

    Lake County Highway Department

    Facilities:

    Two-Lane Roadway in Lake County; Approximately 3 Miles

    Tonnage:

    14,000 Ton Mix

    Services:

    Remove 3" of Existing Pavement and Replace with 5" New Asphalt Pavement, New Stone Shoulders, Concrete Curb Repair and Ditch Landscaping.

    Budget:

    Approximatly $715,000.

    Time Frame:

    Spring of 2003